Phase 3 is complete
OR
Grout is down. Toilet is back in

New bathroom

New vanity, tub tile, floor tile, and floor mat

We finished putting the floor tile in the bathroom on Sunday, which needed at least 24 hours to cure. So we went to work like normal on Monday. I didn’t think I would have enough time to grout Monday night, so instead I put up the sanitary base on the wall between the tub and the vanity. On Tuesday I worked from home, so I started off doing the grout. I woke up around 7, had a quick breakfast, then mixed up the grout. We chose the same color grout for the floor tile as we used for the tub and vanity countertop — parchment. While I was letting the grout slake I got out the utility knife and razor blade and removed any mortar in the grout joints that I had missed with the pencil while laying the tile. I probably started grouting right around 8:00 a.m., and finished around 10:00 a.m.

New tile and grout

The new tile and grout

One detail that the Home Time tile video mentioned about grouting was that there would be a “grout haze” when done, which I would need to wipe off. I had not noticed any haze when grouting the tub or the countertop, but I definitely noticed a haze on the floor tile. I think I might have been a little more paranoid about wiping off the grout with the sponge for the previous tile projects, or maybe the difference lay in the fact that the floor tile is slightly textured, so it is more difficult to get all the grout out of the small dips in the tile surface, or maybe a combination of both. I had remembered that the video said to wipe off the grout haze with a clean towel, but I couldn’t remember when, so I went and watched part of the video again, and realized that they recommended doing it as soon as possible, and to simply step on the tiles, being careful not to step on the grout joints. So I spent 20 minutes or so doing that, and got off most of the haze, though I will probably have to go over it one more time.

Close-up of drain

Close-up of the floor drain. I tried to even out the edge with grout

After dinner on Tuesday I decided to put the toilet back in, figuring that the grout would have had sufficient time to dry. It wasn’t completely dry, so I was careful to not step on the grout joints. I took the rags out of the toilet drain which were preventing the sewer gases from coming up, and removed the rest of the old wax ring with a chisel (I didn’t need a chisel, but the wax is really sticky, and I didn’t want to scoop it up with my hands, so it worked pretty well). Then I spent a good 20 minutes cleaning the toilet, and then finally started to put it in. We weren’t sure exactly what sort of wax ring to get, so we got several — one deluxe wax ring, one deluxe wax ring kit (with new nuts, bolts and washers), and one non-wax ring kit. I decided to dry the simple deluxe wax ring first. Although the tile video showed putting the was ring on the drain hole, and then setting the toilet on it, the instructions on the wax ring said to put it on the toilet first, and then set it on the hole, so I followed the instructions that came with the ring. The tile video mentioned I might need some plastic shims to keep the toilet from rocking, but it didn’t seem like the toilet was rocking at all to me, so I didn’t worry about it (especially since I only had wood shims).

sanitary base

The sanitary base between the tub and the vanity

I did make 2 mistakes. When I got ready to put the nuts on the bolts, I noticed they were pretty rusty, so I decided to open up the package of nuts and bolts in the other wax ring kit, and then promptly realized that the new nuts would not fit on the old bolts. So I just stuck with the old washers and nuts, and wasted a dollar or two. The second mistake was trying a new gasket that sits between the toilet base and the tank. The old gasket seemed ok, but I thought a new one would be good. Clare had bought one at Pell’s that looked a bit different from the old one, but it did say that it was for a Gerber toilet, which is what we have. (Sidenote – Kathleen Harriman said she has toilet envy of our cool pressurized Gerber toilet, which Steve Harriman installed for us). I had quite a time getting the tank to sit right using the new gasket, and several test flushes, I realized that it was leaking just a bit from that seal, so I went back to the old gasket. Unfortunately, I had already put on the new $30 toilet seat at this point, and scratched it up a bit removing the tank. Oh well. Nothing I can do about that. After putting the old gasket back on it seemed to be leak-free. I then went around and caulked around the toilet, between the tub and the tile, and between the floor tile and the sanitary base. I am still not very good at caulking.

toilet back in

The toilet is back in, with a new seat, and some fresh caulk

We still have lots of work to do in the bathroom, but the 3 major projects are complete — (1) the tub surround, (2) the vanity, and (3) the floor tile.

Order of operations
OR
Tile is on the floor

putting in new insulation

Ready to put in some new insulation

So we finished the vanity about a week ago, and had planned to do the floor tile next. Part of our bathroom project involves building some sort of shelves/cabinet where the washer and dryer used to be, since otherwise we have some empty space, and also because we want to hide the plumbing where the laundry tub used to be. I had been thinking for some time that we would want to put the shelves in before tiling the floor, but we still haven’t really figured out exactly what we are going to do for that, and it started to seem like we might never get floor tile down if we waited. Eventually I decided that we could do the floor tile first, so we decided to do it this weekend, hoping that it will be done by the time my parents come to visit next weekend.

All the old tile is out

All the old tile has been ripped out. Now just a bit more cleaning to do.

The plan was to get all the prep work done Friday night, then put in the tile on Saturday, and grout Sunday. We left work a little later that we had expected on friday, and then we also ended up talking with the Harrimans for quite awhile. We stopped there to pick up the tile saw that they agreed to lend us, in exchange for helping them with their website. As to be expected, we got talking about our respective projects. They have more than we do, but hey, we are still novices. So we got home a little after 8, heated up some leftovers, then got working on getting the toilet out. That was actually no problem at all. I shut off the valve, then flushed the toilet, which got most of the water out, but not all. Clare had the brilliant idea of getting most of the remaining water out of the bowl using a cup, which worked quite well. A bit of water spilled when I lifted up the toilet, but not that much. After lifting the toilet off, we stuffed some rags in the hole to prevent sewer gases from getting out. We put the toilet in the foyer temporarily.

new drywall is up

New drywall is up

Then I got to work removing the rest of the old right around the toilet. I worked on this until about 10:30 or so, then decided I would finish up in the morning. In the morning I finished getting off the last bit of tile, and also worked on ripping out more of the drywall around the toilet that had gotten moldy. Clare and Liz were working on cutting the new drywall when I thought I noticed more termite damage on the nailers behind the old drywall. It turns out that it was not termite damage, but that some of the insulation was a bit moldy. So I ripped out about 10 square feet of the insulation and put in some new stuff, and a new vapor barrier there. Though I had poo-pooed the purchase two weeks ago, the staple gun that Clare bought came in very handy. Then we started hanging the drywall. Unfortunately most of the pieces were about 1/4 inch too big, so we spent quite a bit of time whittling them down with the utility knife until they would fit. This time, unlike last, I marked the location of the studs before hanging the drywall, which made life much easier. So most of Saturday was consumed with drywall and sweeping up the bathroom. Clare and I did get some of the tile out and talk about the best layout plan. We decided on doing full tiles by the doorway, which means we will end up with some pretty small tiles right by the vanity, but they should not be too visible. I finished the day with 2 round of mopping, so that the surface should be nice and clean, and the mortar will adhere well.

Clare cuts some tile with the tile saw

Clare cuts some tile with the tile saw

Sunday morning we got out of bed around 7:30. For some reason Clare wanted to shower, but I got straight to work (after a bowl of cereal and a cup of coffee). The first thing to do was to finalize the layout, which involved setting some of the tile on the floor (without any mortar), and making sure everything was straight, then marking the position of the tiles using a chalk line. Once this was done, I could start measuring the first few cuts that we need to make. This is one way in which we deviated from the instructions in the HomeTime tile video. They recommended laying all of the field tile first, then waiting a day and laying the edge tile. Since we had so few field tile to lay, this seemed like overkill, and we were anxious to get the project done, so we can put the toilet back in. I mixed up the thinset mortar and began making measurements while Clare got the tile saw and tile cutter ready. Since the tile saw sprays some water around, we decided to do it outside. It turned out to be a nice day — partly sunny and 55 or so — but it was only about 35 when we started at 9 a.m. Clare was a real trooper though.

Combing out mortar

Combing out mortar

I probably laid down the first few tiles around 9:30. It is best to work in relatively small sections, so we made 2×2 or 2×3 boxes with the chalk line. I began by scooping some mortar out of my bucket with a margin trowel, then I used the smooth side of my notched trowel to comb it out. I chose a trowel with 1/4″ wide notches with 1/4″ spaces and 3/8″ deep. The tile video recommended 3/8″ deep for tiles 12″ or larger. Our tile are 13″ (actually 12 13/16″ — to make it easy to do measurements using a 3/16″ grout joint. We decided to use a 1/4″ grout joint). After spreading out the mortar with the smooth side, I then combed it out using the notched side. This gets the proper amount of mortar down. I filled one 2×2 box with field tile, then set a few cut pieces which Clare had cut very nicely. After I had set the cut pieces, I removed one of the field tiles, to check to see how well my mortar was adhering (also recommended by the Home Time tile video). According to the video, the mortar should cover about 90% of the tile. If it is less than this, then the mortar is probably too dry, or if greater than 90% the mortar might be too wet. I thought my test tile was more like 70%, so I added a bit of water to the mortar, and also concentrated on getting a consistent 45° angle with the notched trowel. I then replaced re-combed the mortar where I taken the test tile out, and put down a fresh tile.

test tile

Test tile. Is there enough mortar?

I continued laying tile for several hours, and Clare continued cutting tile. For all the straight cuts we used a simple tile cutter which scores the tile and then snaps it. But for the trickier cuts, we used the tile saw. The tile saw has a circular blade with a diamond edge. It is not jagged like a circular saw though. The saw sprays water on the blade as it is cutting to keep down the heat and the dust. Clare used one neat technique with the saw to get some rounded cuts, which we learned from the video of course. She made several very skinny cuts into the area that we wanted to remove, then nipped them off using the tile nippers.

fancy cuts with the saw

Clare makes a fancy cut with the tile saw using the many teeth method.

I continued laying tile until about 1 p.m. or so, at which point I decided I need a break, so Clare and I had some lunch. By this point we were mostly done, and had mostly field tile to lay down. As I started to lay tile after lunch I started realizing that the tile was deviating from the chalk lines. I began to get worried that the tile was not going to fit how we had envisioned. So I put down a few tiles and sure enough, it looked like we might end up cutting tiles by the doorway, which is exactly what we were trying to avoid. So I consulted with Clare, and we decided to just squish some of the grout lines instead of cutting the tile.

all the tile is laid

All the tile is laid

I finished laying tile around 3:30 or so, and then spent about a half hour cleaning up. Now we have to let the mortar set-up for at least a day. Hopefully we can grout tomorrow, then put the toilet back in soon.

Spring break
OR
Daffodils sprouting

sprouting daffodils from afar

Sprouting daffodils seen from afar

Last weekend marked the beginning of Indiana University’s spring break. This doesn’t mean we get a week off, but it does mean less traffic congestion. And more importantly, it means that spring is on our doorstep. It has been very nice this week; sunny and in the 40s or 50s. This is a welcome change from all the freezing rain and gray of February. I was feeling grumpy Saturday, one of the first days of nice weather, so Rob and I decided to go on a walk around the property. It was very wet. We crossed the stream and went back to the field, pond, and up the hill to where Rob usually gets the wood he so enjoys chopping. When we reached the pond, we found that it was full enough to cover the drain pipe, which leads down to the field. That explains a lot. The ice on the pond was cracking and sinking, a sign of spring emerging.

Daffodils up closer

Daffodils a bit closer

When we came back down from the pond and the woods, we walked around the planned garden sites and talked about what to plant where. We also discussed whether or not to get chickens some more and if we did where to put the chicken coop. Then, almost done, we went to throw away some garbage we found on our walk. That’s when we saw the most definitive sign of spring: daffodils.

daffodils up very close

Daffodils up very close

Poking up through the dusting of snow and last fall’s leaves, little green blades and buds stuck their heads out to let us know that the annual cycle is complete and spring is on it’s way. The spirit of renewal and rebirth reminds us that we will try it all again this year and see where life leads us.

We spent the next half an hour or so clearing brush and leaves to give our newest arrivals a hospitable welcome.

Phase 2 complete
OR
Vanity installation finished

This past weekend we finally finished the vanity installation. We worked on it a bit almost every night of the week.

tile is laid

the countertop tile is down

Monday night we got home around 6:15, and brought pizza with us, so we could get working on the tile pretty quickly. I started mixing up the mortar, and ended up getting really lucky and mixed the last part of one 25lb bag, which ended up being just about enough for the countertop. While the mortar was slaking, we started laying out the tile on the countertop to determine where we wanted to make our cuts. We decided to make cuts on the side next to the half-wall, since it would be less visible when you walk in the room. Then I marked the cuts for the sink-hole, and Clare set off making those cuts with the tile nippers while I started laying tile. Liz also helped cut some of the tile for the edge pieces using the tile cutter. The tile went on quite easily, though after it cured, I realized that they weren’t completely level. Hopefully I will be able to get them a bit more level when we do the floor tile. The actual laying of the tile only took a couple hours.

The new vanity

The new vanity with the sink installed

Tuesday Clare and I worked from home, so in the morning I started off by putting on the backsplash. We used 4×4 bullnose tile for the backsplash, and put it on with pre-mixed mastic, just like we used for the tub tile. That only took a half-hour or so. Then I worked until dinner-time, and after dinner I put on the grout. While I was putting on the grout, Clare and Liz worked on getting the old faucet off the sink. This proved to be trickier that one would think. The faucet part came off pretty easily, but the drain simply would not come off. The ring that fits in the sink would not come unscrewed from the rest of the drain. After I was done with the grout I took a look at it, and tried using some WD-40, but it didn’t help much. So I decided to let it soak in for a day.

countertop with tile and sink

Countertop with new tile and sink installed

Wednesday evening I set about trying to get the drain off again, hoping that the WD-40 would have helped overnight. It didn’t. So finally I got out the hacksaw and simply cut off the drain. Then I spent close to an hour removing the old caulk from the sink with a razorblade, and getting as much rust off the bottom of the sink where the old bolts had been as I could. Once again, I decided to call it a night.

Decorative tiles

Decorative tiles (they match the tub)

Thursday evening I finally installed the new faucet and put the sink in the hole. I attached the flexible hoses that were connecting the old faucet to the new faucet, and connected the first half of the drain assembly, putting a little silicone sealant under the metal rim that sits in the sink bowl, per the instructions. Then I put some more silicone under the rim of the sink, and set the sink in place. Finally, I put a little silicone between the edge of the sink and the tile. I finished connecting the supply pipes and the drain assembly, but did not turn the water on, because I wanted the silicone to cure.

Sink back in

New faucet, old sink

Friday evening I tried out the sink. I followed the instructions and took out the aerator to flush out any debris that might have gotten into the pipes while ripping out the old vanity. I had to tighten the supply pipes a bit more, but then it seemed to stop leaking. I was initially disappointed when I tried to put the aerator back in though. A small stream of water was obviously not flowing through the aerator, but spraying around. I tried tightening it down with a plier (and a rag to prevent gouging the aerator ring), but it didn’t help. Then I took it off, thinking it might be misthreaded, and tried again. Still no luck. Then I happened to notice some black thing peaking out of the sink drain hole, from under the stopper. It was a washer! It must have fallen out when I took the aerator out, or when I turned the water on. Once I put the washer on, the aerator worked fine. Then I spent a good 20 minutes or more working on adjusting the stopper. It seemed to be the appropriate height, but when I pulled it up, it fell right back down. I decided to call it a night and work on it over the weekend. I did caulk between the countertop and the backsplash though, using the Polyseam Seal caulk my dad recommends. This time I tried using masking tape to avoid getting the caulk where I didn’t want it. I was not that impressed with this method, as it seemed like I had to smooth out the caulk a second time after removing the tape.

Vanity up close

The new vanity up close. It has a burgundy finish

Saturday was a nice day, and I ended up spending most of the day doing other stuff besides the bathroom. On Sunday I went back to working on the stopper and checking for leaks. It turns out that the drain was leaking just a bit. I ended up just undoing some of the PVC connections and then re-tightening them, which seems to have done the trick. I also discovered that the reason that the stopper was falling down was because I had not tightened the nut that holds the ball in the drain pipe enough. Once I did that it worked fine.

So, phase 2 is complete. This next weekend we hope to work on Phase 3 – the floor tile.

Surprise! termites
OR
Installing the new vanity

removing old vanity

Halfway done removing the old vanity

This past weekend we set out to install the new vanity in the bathroom. I was figuring it would take a total of 3 or 4 days, including some waiting time, since we were planning on tiling the new countertop. Friday night after getting home from work I eagerly started working on removing the old vanity. I went to take out the sink, but soon realized that the shelf under the sink was in the way of undoing the plumbing, so I started by removing the doors and the trim, which allowed me to get out the shelves. Then I went to turn off the water. After some WD-40 and a little elbow grease, I was able to shut off the water and disconnect the plumbing. Then I ran a utility knife under the sink rim to break the caulk, and then was able to push up on the sink from underneath and wriggle it free. I then worked on removing the countertop and disassembling the rest of the vanity using a hammer and prybar. We might try to reuse parts of it, so I was pretty careful to try to save as much as possible.

looking down at the pipes

Looking down at the pipes through the sink hole in the old vanity

Once I had all of the vanity out, I started ripping out rest of the drywall. Here comes the surprise. At first it seemed like some of the 2×6’s behind the drywall were rotten, but after further inspection, it became clear that it was termite damage. This was definitely going to set back a little bit. I continued ripping out drywall for awhile longer, then decided to call it a night.

termite damaged wood

Some of the termite-damaged wood

Saturday morning we slept in until 8, then got working on the bathroom around 8:30. Now I got a better idea of the extent of the termite damage, and we ended up calling Dave and Ellen to get their opinion on how best to proceed. I was thinking about replacing the termite-eaten 2×6’s, but they recommended just putting in a couple additional 2×4’s to have something to nail the drywall into,since some of the exterior siding may be nailed into the termite-eaten 2×6’s. I did replace the insulation though, and Clare and Liz put up a new moisture barrier. At this point I went outside to enjoy the day and cut up some firewood, and left Clare and Liz to hang the drywall. After they got done with that, I helped Clare tape and mud the drywall, and that was pretty much a day.

Rob removing nails

Rob removes old drywall nails

Sunday morning we got up around 7 and got to work. Clare sanded the drywall mud while I worked on making some fresh bread. Then I washed the walls and put a coat of Killz mold-resistant primer on the new drywall. We let that dry for about 4 hours, and worked on some other projects in the meantime, like splitting wood.

Clare sanding drywall mud

Clare sands the drywall mud

While the primer was drying, I also took the vanity out of the box, and started reading the installation instructions. I was a bit surprised to find that most of the back of the vanity was completely open. It also seemed like there wasn’t very much holding the drawers up. Although the old vanity was not quite as finished-looking, I think that it was probably sturdier. That is one thing that I have been learning as we do home improvement projects. A lot of building materials are actually fairly fragile, especially all the finishing touches.

Vanity is in place

Vanity is in place

After taking the vanity out of its box and marveling at how finished it looked, I immediately set out to cut a big hole in the bottom of it for the pipes. I suppose that part of the reason that the back is open is that the assumption is that the pipes are coming out of the wall, not the floor, but ours come out of the floor. My friend Sean leant me his jigsaw, and also gave me the advice of putting some packing tape over the part where you are going to make a cut, to help prevent splintering. I measured the distance from the walls to the pipes, then used those measurements to mark my hole in the vanity. By the time I was done making the hole, it was about time to put the vanity in. Clare helped me carry the vanity into the bathroom and get it shimmed. I only ended up screwing the vanity into the wall in 2 places, since I hadn’t put in that many 2×4’s behind the drywall,but since the vanity is resting on the floor (well, on the shims which are on the floor), I didn’t worry about it too much.

Testing the hole for the sink

The sink fits in the hole!

Once I had the vanity shimmed and screwed in, I set about making the countertop. After much searching, we decided on tiling the countertop. We weren’t very pleased with any laminate countertop options, and marble or granite just seemed out of our price range. We also had a pretty good experience tiling the bathtub, and the countertop seemed like it would be easier in many ways. Once again, we watched the Hometime tile video to see how to proceed. They recommended using 3/4″ exterior grade plywood, with 1/2″ cement board on top of that. One thing I had noticed when Clare was putting up the new drywall was that the space for the vanity was not exactly square. The space in front was 54″, but by the wall it was only about 53 1/2″. I took this into consideration when cutting the plywood and cementboard. Since we had a 54″ space, we ended up getting a 48″ vanity, since they only come in full foot increments. Originally we thought we would center the vanity and put some 3″ wood spacers to fill the gaps, but it turns out that Lowe’s (where we bought the vanity) did not have any spacers in the right color. So, instead we decided to leave a 6″ gap on one side, but to have the countertop fill the whole 54″. This left the option of centering the sink on the counterop or on the vanity. We decided on the vanity, so I put that into my calculations for where to cut the hole in the plywood and cementboard for the sink.

The tile underlayment

The tile underlayment. Notice the parts where the cement board is broken.

Unfortunately I had some problems cutting the hole in the cementboard. I followed the Hometime suggestion of putt the cement board on top of the plywood and then tracing the hole from the bottom. The problem was that I was supposed to flip the cementboard over and trace the other side as well, but because the area wasn’t exactly square it wouldn’t fit the other way. So I tried copying it just by guessing, which didn’t work out very well, so then I decided to try to use the Saws-all to cut the hole, which was working pretty well until the cementboard broke in half. I managed to put the pieces back together, and I think it shouldn’t be a problem.

Our next post will detail the actual tile laying.