Phase 3 is complete
OR
Grout is down. Toilet is back in

Wednesday, March 19th, 2008
img_5396

New vanity, tub tile, floor tile, and floor mat We finished putting the floor tile in the bathroom on Sunday, which needed at least 24 hours to cure. So we went to work like normal on Monday. I didn’t think I would have enough time to grout Monday night, so instead I put up the [...]

Order of operations
OR
Tile is on the floor

Sunday, March 16th, 2008
img_5339

Ready to put in some new insulation So we finished the vanity about a week ago, and had planned to do the floor tile next. Part of our bathroom project involves building some sort of shelves/cabinet where the washer and dryer used to be, since otherwise we have some empty space, and also because we [...]